Engineering News · 25 September 2026

HS2 Installs First 55m Span of the New Saltley Viaduct in Birmingham

A bank holiday move over live railway lines shows off-site assembly at work

The existing Saltley Viaduct crossing the Grand Union Canal in Birmingham

Engineers working on HS2 in Birmingham used the August bank holiday weekend to install the first span of the new Saltley Viaduct. The 55-metre span was assembled away from the railway and then driven around 125 metres into position over the Birmingham to Derby lines on self-propelled modular transporters (SPMTs) during a temporary rail closure. Passenger services were back on schedule the next morning.

Why Saltley Viaduct is being replaced

The existing Saltley Viaduct is 183 metres long. It has to be rebuilt higher so that HS2 trains can pass safely underneath it on their way into central Birmingham. The replacement is being delivered by Balfour Beatty VINCI (BBV) working with Network Rail.

The new viaduct will also be 4.5 metres wider than the old one and will include LED-lit walkways, which should improve the route for pedestrians and cyclists as well as for traffic.

Self-propelled modular transporter axles used for heavy lifts

Moving 55 metres of bridge on wheels

SPMTs are computer-controlled, multi-axle platforms that can carry very heavy loads and steer with great precision. By assembling the span next to the railway and then driving it into place, the team kept the time the railway had to be closed to a minimum. Rail closures, known as possessions, are tightly controlled and costly, so shifting work off the live railway is one of the most effective ways to protect a programme.

It is a technique that relies on close teamwork between structural, temporary works and mechanical engineers, as well as specialist heavy-lift operators.

Four spans and a new river bridge

The first span is the start of phase one. HS2 says a second, 35-metre span will be lifted in by crane over the new HS2 line in October 2026, with spans three and four, crossing the Birmingham and Warwick Junction Canal, due later in 2026. Tie-in works and a new bridge over the River Rea will follow, and the viaduct is expected to open to the public in November 2027.

HS2 project manager Nic Ryder said the engineering team was making fantastic progress, while BBV senior project manager Dan Binns described the viaduct as the latest HS2 structure to take shape in this part of the city.

HS2 construction on the Birmingham skyline

The skills behind heavy-lift bridge moves

Moves like this depend on a wide range of specialists: bridge and temporary works designers, steel fabricators, rail possession planners, SPMT operators and site engineers who can work to millimetre tolerances. With several HS2 structures being built around Birmingham at the same time, demand for these skills in the West Midlands is strong.

Explore our civil engineering recruitment services, or contact the Bernoullis team to talk about your next role or project.

Sources: HS2 media centre · New Civil Engineer · RailAdvent

Images are illustrative. Credits: A J Paxton , CC BY-SA 2.0 via Wikimedia Commons; IMessmer, CC BY-SA 3.0 via Wikimedia Commons; Robin Stott , CC BY-SA 2.0 via Wikimedia Commons.

FAQs

Frequently Asked Questions

Who Are Bernoullis?

We Are The Number One Engineering Recruitment Firm In The Uk! We Pride Ourselves On Getting The Best Prospects For Each Vacancy We Fill... No More Time Wasted With Interviewees Who Are Not Up To The Job!

Keep reading

More Engineering News and Career Guides

Next steps

Ready for Your Next Engineering Move?

Browse live engineering vacancies, send us your CV or tell us about a role you need to fill. Our engineers recruit engineers.

New AI Job Matcher

Not sure which jobs to apply for? Let AI match your CV to 150,000+ live UK jobs.

Upload your CV once and every job is scored against it, best fits first, with the skills you have and the ones you’re missing.

  • 150,000+live UK jobs
  • 0–100score on every job
  • Nightlyfresh jobs every day

3-day free trial, then £11.99/month. Includes CV rewrites for every job. Cancel online any time.

Site map

Submit Your Vacancy

Please fill in the form below.

Drag & Drop your file here or click to browse

Submit Your CV / Resume

Please fill in the form below.

Drag & Drop your CV here or click to browse